Projected Timeline for Meetings & Activities

Group Meetings


March 8, 2011

Initial Meeting: Introduce process & timeline; Begin BRC approval tasks

Other Activities




Set working groups (WG); schedule WG meetings; develop tools for use in WGs; develop contact lists and publish for BRC, Planning Team and WGs; line up SMEs


June 7, 2011

Presentation: "Lessons" Learned
Discussion: Progress & Next Steps


Update on WG progress; get BRC engaged in developing constituent and political support; August- draft GOS, and send to BRC

September, 2011

Progress Reports- all groups
Select Review Committee


Oct-Nov draft outline structure for Plan and send to BRC

December, 2011

Review Goals & Strategies
Review outline structure


Fill in gaps on missing information/data; get finalized Recommendation Memos from WGs


March 2012

Update meeting


March-May 2012 draft plan; Planning Team reviews draft; draft to BRC for comments; Begin planning for "unveiling" of Plan Complete final edits and review

June 2012

Review plan with full BRC


Complete final edits and review

August 2012

Public signing and media announcements



Letters of Service to all participants